Tex-Al Extension, Upgrade and Pathway

Description

The purpose is to connect and upgrade Tex-Al Drive between Palmer-Fishhook and Wasilla-Fishhook, providing a new connection and pathway.

This project was approved by voters on the 2021 bond package.

Current Fact Sheet

Schedule

Construction is anticipated to begin in 2027.

Status

The majority of the right-of-way is in place for the connection between the west Tex-Al and east Tex-Al roads. The project team is beginning the right-of-way acquisition phase for the remainder.

Design

Typical Cross Section

Plan Views, West End to East End

Plan view 1: Wasilla-Fishhook Road, Frozen Court, and Backroad Circle

Plan view 2: N Grouse Loop and N Slaton Street

Plan view 3: N Steen Road and N Sun Circle

Plan view 4: N Engstrom Road and N Covington Street

Plan view 5: Start of curve

Plan view 6: E Windy Woods Loop and N Trinity View Drive

Plan view 7: E Alpine Meadow Drive and Strawberry Circle

Plan view 8: Strawberry Circle, N Kettle Drive, and Palmer-Fishhook Road

Benefits

Currently there are no east-west connections that are constructed to collector road standards between the two Fishhooks north of Trunk Road. This project:

  • Improves area traffic and pedestrian circulation.

  • Provides an alternate route between the two Fishhooks.

  • Shortens commuting and emergency response times.

Cost

Estimated total cost: $14,800,000.

Project team

Andrew Strahler

Civil Construction Project Manager, Matanuska-Susitna Borough